NR-34, item 34.14.2.1, requires that tightness tests be performed only by workers who have been trained in the Basic Safety Course in Tightness Testing described in Annex I, item 5, of the standard - a 24-hour initial course made up of an 8-hour theoretical module and a 16-hour practical module. A tightness test is a non-destructive test carried out by applying pressure to a part, compartment or piping in order to detect leaks (item 34.14.1); it is not a hydrostatic strength test, and confusing the two is a recurring source of accidents. The purpose of this course is to qualify the worker to prepare, execute and close a tightness test safely: to check the four mandatory components of the test system, to isolate and signal the risk area, to raise pressure gradually and block it at the test pressure, to depressurise through the relief valve, and to recognise the prohibitions that apply while the system is pressurised. This blended variant delivers the theoretical module by e-learning and keeps the full 16-hour practical module face to face, so that the hands-on requirement of Annex I, item 5.2, is preserved in full while classroom time away from the yard is reduced.
01
02
03
04
LO1 - Identify the scope, structure and main safety requirements of NR-34 item 34.14 for tightness testing activities.
LO2 - Differentiate the roles and responsibilities of trained and legally qualified professionals involved in tightness testing.
LO3 - Recognise initial and refresher training requirements and the requirements for maintaining training records and documentation.
LO4 - Explain the basic principles, purpose and application of tightness testing and differentiate it from hydrostatic testing.
LO5 - Differentiate gauge pressure, absolute pressure and vacuum and interpret relevant physical quantities and unit conversions.
LO6 - Interpret readings from calibrated instruments, considering their range, resolution and measurement conditions.
LO7 - Identify applicable technical standards and interpret qualified tightness test procedures, parameters and acceptance criteria.
LO8 - Recognise documentation and traceability requirements applicable to tightness testing activities and results.
LO9 - Identify the mandatory components of a tightness test system and their functions.
LO10 - Recognise requirements for safety valve settings, pressure gauge calibration and test system design and calculation documentation.
LO11 - Identify safety requirements for exposed joints, flexible lines, safety cables, component removal and system isolation.
LO12 - Differentiate applicable tightness test methods, including positive pressure, vacuum box and capillarity methods.
LO13 - Identify hazards and risks and apply basic risk analysis techniques to tightness testing activities.
LO14 - Interpret the Preliminary Risk Analysis (APR), including applicable hazards, risks and control measures.
LO15 - Explain requirements for issuing, validating, suspending and closing the Work Permit (PT) for tightness testing.
LO16 - Identify the safety measures and controls to be verified before authorising a tightness test.
LO17 - Identify collective protection measures, safety signage and PPE required according to the test method and associated hazards.
LO18 - Recognise safety restrictions and prohibited activities applicable while the system is pressurised.
LO19 - Determine risk-area limits and isolation requirements and identify the requirements for access control, release and visual identification.
Objective - Demonstrate preparation for the practical activity, including safety briefing, PPE, Work Permit, APR, area isolation and applicable controls.
LO21 - Demonstrate the pre-test inspection of the test system, equipment and safety devices to confirm readiness for safe execution.
LO22 - Perform, under supervision, an applicable tightness test method in accordance with the relevant test procedure.
LO23 - Apply and control the test parameters required by the selected tightness test method.
LO24 - Apply the appropriate leak-detection technique and identify and interpret indications observed during the selected test method.
LO25 - Respond appropriately to abnormal or unsafe conditions, applying stop-work, area control and communication requirements.
LO26 - Demonstrate safe test completion, including pressure or vacuum relief where applicable, equipment removal, restoration and recording of results.